26.04.2024
The Status of Work at the Sikorski Residence Construction Site
Update from the construction of the Sikorski Residence development.
Sikorski Residence Phase I (Buildings A and B):
The underground section of Buildings A and B has been completed. The ceiling over the underground car park has been concreted. The ceiling over the ground floor of Building A and the walls of the ground floor of Building B are being constructed.
Sikorski Residence Phase II (Buildings C and D):
The foundation slab under Buildings C and D is underway.