Sky Trust – Construction Progress

See the progress of works on the Sky Trust development in Kielce.

Construction works to date have been mainly focused on site preparation. Below is a summary of the works completed:

  • construction site has been secured and fenced off,
  • electricity connections have been made,
  • existing connections interfering with the underground car park have been partially removed, further work will continue in September/October,
  • construction site has been tidied up and preliminary earthworks have been carried out for the installation of slurry walls,
  • an access road has been constructed,
  • construction site facilities (site office, social and storage containers) have been set in place.

In addition, the following preliminary construction works have been carried out:

  • sheet pile walls with ground anchors have been installed
  • walls and columns for the underground car park have been partly built
  • intermediate floor (underground car park floor slab) is partly finished
  • the first working section of the floor above the underground car park is being reinforced (ordinate -0.40)

Feel welcome to view photos from the construction site.